Testing of Cables|What are the test for cables?|Quad cable testing
Contents:
- TESTING OF CABLES
- Why cable testing is needed?
- What are the test for cables?
- How many types of cable testing are there?
- How do you test the quality of a cable?
- Detailed Testing Procedure
Why cable testing is needed?
The cable must be tested for continuity,
insulation, and attenuation. The test should be carried out before and after
cable laying. For maintenance purposes, these tests shall be performed
every year before and after
the monsoon.
How many types of cable testing are there?
Types of tests on quad cables
Test of quad cable may be classified into four parts.
1. Test during laying of cable.
2. Test after cable laying.
3. Routine tests
4. Tests during localization of fault.
What is the test for cables?
Types of tests
Test of quad cable may be
classified into four parts.
Test during laying of cable.
Test after cable laying.
Routine tests
Tests during localization of
fault
1.
Tests during laying of cable
Test
the cable for proper end ceiling. Check up the cable throughout the length for
any physical
Damages during transportation
and handling and for manufacturing defects.
Tests
for continuity and insulation before laying the cable.
2.
Tests after cable lying:
a. Test
for continuity.
b. Test
for insulation.
c. Test
for attenuation.
d. Test
for crosstalk (FEXT & NEXT ).
Precautions while testing a cable
All working circuits and power supply shall be
disconnected from the cable at both ends.
Communication between the ends of the cable under test shall be established by
magneto telephones with other cable/ cable under test if possible otherwise by
VHF sets.
Competent staff required
instruments and material shall be available at both the ends.
Testing shall be carried out when conductors and insulated parts like terminal
blocks are clean and
dry.
Cable
conductors shall be earthed momentarily to discharge the accumulated charge, if
any, before
the commencement and after the
end of insulation testing.
Detailed procedure for testing of cables
1.
CONTINUITY TEST:
This test is carried out to
confirm that core under test is either showing break or not. Testing can be
done as follows:
Set
the knob of multimeter to check resistance at suitable lower range at one end.
Loop
the pair at the other end.
Connect the probes of mulitmeter to the both limbs of the pair.
Deflection of mulitmeter needle shows the limb is ok, otherwise there is a
break in the limb under test.
Repeat the procedures for testing of other pairs
The
standard value is 56 ohms /loop km or 28 ohms per km ( each conductor)
The above procedure is adopted
for testing of continuity of terminated cable including armour continuity.
2.
Insulation test of cables
This test is carried out to
measure insulation resistance of the cable.
Insulation resistance measured
(i) Between conductors to
conductor,
(ii) Between conductor to
earth.
Procedure:
(i) Insulation resistance Between Conductor to conductor
1. A 500-volt insulation
tester or megger is used for this test.
2. Pair of Conductor for which
insulation to be measured shall be connected to line and earth terminal of the
megger.
3. Now rotate the handle of
the megger or press the push button of the megger, Reading of the megger shows
the insulation between conductors.
4. Replace the conductor
connected to the earth terminal of megger by other conductor of cable and take
measurement.
5. Repeat process (4) for
remaining conductors.
6. Now connect next conductor
to line terminal of the megger
& connect the remaining
conductors one by one to earth terminal of the megger and take measurements as
per procedure 3, 4& 5.
7. The standard value is 5,000
mega ohms/km.
Insulation resistance Between Conductor
to Earth
By this we can measure
individual insulation of conductors with respective to earth.
Connect conductor under test to the line terminal of the megger.
Connect earth terminal of the megger to the earth.
Rotate the handle of megger or press push button of megger. The reading of
meter will show the insulation resistance of the conductor. Insulation reading
shall be recorded after applying the test voltage for about a minute till a
steady reading is obtained.
Replace the conductor at Line terminal of the megger by another conductor under
test and repeat the
procedure as above.
The
above measurements can be adopted for terminated cable.
3.
Attenuation test of cables
Instruments to be used:. Transmission
measuring set (TMS)
Two
TMS sets are required for this measurement.
One
set is kept at one end of the cable and the other at other end.
Before commencing test the zero errors of the both meters to be checked and
corrected.
Feed
0 db at 800 Hz tone from one end(sending end) and measure the receive level at
the other end
(receiving end)across 600ohms
impedence.
The
transmission loss, return loss, insertion loss are measured using this method.
The
standard attenuation values are
(a) 4.4 dB/KM at
150KHz( unloaded cable)
(b) 2dB /KM at
300-3400HZ ( unloaded cable)
( C ) 0.25 db /km at
800hz (loaded cable)
4.
Cross talk test : Far end Near end
Instrument used- Cross talk
measuring set. Oscillator 150 KHz or 800Hz.
Feed
test tone of 0 db at 150 kHZ on one pair and measure the Near end and far end
cross talk terminated at 600 ohms load impedence on the other pair of the same
quad.
Also
the cross talk has to be measured in adjacent quad.
Cross
talk is measured at near end and also at far end. Cross talk attenuation
between any two pair
space insulated VF pair at
150KHz shall not be less than -67.8 dB
The
near-end cross talk shall not be less than – 55 dB.
5.
Routine tests
Under
ground cables shall be tested once in every year with megger for insulation
only and the
results of tests shall be
submitted to DSTE/ASTE
Apart
from the testing to be performed during laying and after laying the cable,
routine tests
shall also be conducted on the
cables to ensure that the cable is in good condition.
This will provide the data to
decide as when a cable has served its life and to replace the same in time, to
avoid complete breakdown.
All
spare pairs in a cable shall be tested periodically once a year to ensure that
they are in good condition. This will help in using the same pairs whenever a
working pair has been faulty and the circuit carried by it has to be
transferred to one of the spare pair.
0 Comments
You can give your Suggestions and feedback here